Anticipated Project Schedule
Exit 18 - Mount Rose Avenue |
| Notice to Proceed to Consultant Project Team |
Spring 2005 |
| Conceptual Design / Environmental Investigation |
Summer 2005 - Fall 2008 |
| Intermunicipal Coordination Committee Meetings |
On Going |
| Public Meeting |
Spring 2009 - Summer 2009 |
| Environmental Clearance |
Fall 2008 |
| Design Field View |
Spring 2009 |
| Final Design |
Fall 2009 - Summer 2011 |
| Right-of-Way Acquisition* |
Fall 2009 - 2011 |
| Construction* |
Spring 2012 - 2014 |
| * Pending the availability of funding |
|