PennDOT District 8-0

PROJECT SCHEDULE

 

Anticipated Project Schedule
Exit 18 - Mount Rose Avenue
Notice to Proceed to Consultant Project Team Spring 2005
Conceptual Design / Environmental Investigation Summer 2005 - Fall 2008
Intermunicipal Coordination Committee Meetings On Going
Public Meeting Spring 2009 - Summer 2009
Environmental Clearance Fall 2008
Design Field View Spring 2009
Final Design Fall 2009 - Summer 2011
Right-of-Way Acquisition* Fall 2009 - 2011
Construction* Spring 2012 - 2014
* Pending the availability of funding  

 

Anticipated Project Schedule
Exit 19 - Market Street
Notice to Proceed to Consultant Project Team Spring 2005
Conceptual Design / Environmental Investigation Summer 2005 - Spring 2009
Intermunicipal Coordination Committee Meetings On Going
Public Meeting To Be Determined (TBD)
Environmental Clearance TBD
Design Field View TBD
Final Design TBD
Right-of-Way Acquisition* TBD
Construction* TBD
* Pending the availability of funding  

 